The Newtown Bypass is now complete.The bypass connects the A489 and A483 whilst avoiding Newtown.
Contents
Traffic updates
You can find out about local traffic disruptions due to this project on the Powys County Council website. Information about disruptions on our trunk roads can be found on the Traffic Wales website.
Summary
Project status: the scheme is now in the ‘defect period’ stage of the works. Outstanding works are being completed whilst the road is open to traffic.
Region: mid Wales
Employers agent: Corderoy
ECI contractors: Alun Griffiths (Contractors) Ltd
Designer: Atkins, TACP
Why we did it
The junction joining the A483 and A489 was regularly congested. The industrial development of Newtown was hampered by congestion issues. Improving the junction should help industry grow in this area.
Current progress
The bypass opened in early 2019. The project is currently completing outstanding works. These works should be completed by autumn 2019.
How we consulted
We held a public consultation exhibition in summer 2009 in Newtown.
Proposals discussed the 2010 preferred route plus alternative options and were displayed at a public information exhibition in summer 2013. This resulted in a modified preferred route being announced in spring 2014. The route was viewed by over 600 people at another public information exhibition in spring 2014.
In summer 2015 there was a public local inquiry.
Contact
Alun Griffiths (Contractors) Ltd have a site office on the A483 Dolfor Road open during normal business hours.
For appointments outside of these hours you can contact the project manager Nick Cleary or by telephone on 01686 806682.