Feasibility support from the Energy Service has enabled Rhondda Cynon Taf County Borough Council to proceed with the Coed Ely Solar Farm project.
Summary
The Energy Service supported Rhondda Cynon Taf County Borough Council with early feasibility work for the Coed Ely Solar Farm. The council led procurement and delivery, with construction beginning in February 2025. The solar farm is expected to be operational by September 2025.
Our support
Feasibility studies, early-stage technical and financial guidance, and strategic support for delivery planning.
Technology solution
- Estimated 9,408 solar PV panels installed.
- 6 MW of renewable energy capacity.
- Private wire connection from the solar farm to Royal Glamorgan Hospital.
Investment
- Funded and delivered by Rhondda Cynon Taf County Borough Council with support from the Energy Service.
Impact
- Estimated 7,355 tCO₂e lifetime carbon savings.
- Enough clean electricity to power approximately 8,000 homes.
- Innovative power purchase agreement with Royal Glamorgan Hospital, meeting up to 15% of annual electricity demand, rising to 100% on peak summer days.